Procedure And Criteria For Issuing Exclusive Prospecting Orders(EPOs),Special Grant and Other Permits
b) Special Grant For Coal And Energy Minerals.
c) Procedure And Criteria For Obtaining Special Grant: Other Minerals (PART XIX).
d) Other Permits Issued By The Ministry.
e) Registration/Renewal as a Custom Milling Center (SI 329,2002; SI 178,2006).
f) Gold Jewellery Permit Requirements.
g) License To Deal In Precious Stones In Particular To Cut And Polish Rough Diamonds.
h) Summary Of Procedures Of Acquiring A Mining Title
i) Details Required In Applying For A Mining Title
Procedure And Criteria For Issuing Exclusive Prospecting Orders (EPOs)
1.1 Application is made to Secretary, Mining Affairs Board who:-
1.2 Procedures of acquiring an EPO are detailed on the table below:
Processing Steps for Exclusive Prospecting Orders
STAGE | RESPONSIBILITY | |||
| MAB Secretariat /Legal Services | Zimbabwe Geological Survey [ZGS] | MAB chaired by the Permanent Secretary | Minister/ President |
|
|
| ||
| Checks on: |
|
| |
| Recommends Applications to be noted after above assessment. | Based on available information application is NOTED or REJECTED |
| |
| Publishes checked notice in Government Gazette for objections within 21 days. |
| ||
Invites Company to appear before MAB for interview |
|
| ||
|
| General Notice sent to Minister and then to President for APPROVAL or REJECTION. | ||
|
|
| ||
Accepts or rejects continuation of exploration work. |
|
Mining Affairs Board Criteria For Recommending EPO Applications
1.3 In making the recommendation the Board looks at the following (or should be satisfied with the following):-
1.4 The EPO is transferable with recommendations from the President.
Special Grant For Coal And Energy Minerals
Procedure
1.1 Application is made to Secretary, MAB who:-
Criteria for Recommending Special Grant Applications
1.2 The MAB considers every application brought before it and reports thereon to the Minister with its recommendations, whether the application should be granted or refused.
1.3 In consideration of the application the MAB looks for the following:-
Procedure And Criteria For Obtaining Special Grant: Other Minerals (PART XIX)
1.1 In terms of Sections 291 up to 296 of the afore mentioned Act, special grants are issued for all minerals except Coal, Mineral Oils and Natural Gas which are issued under part XX of the Act.
Procedure
1.2 Application is done to the Permanent Secretary through the PMDs.
1.3 Application requirements:
Other Permits Issued By The Ministry
1.0 Certificates for Registration as an Approved Prospector
1.1 An applicant should: be 18 years old, a Zimbabwean, pay a non-refundable prescribed application fee.
1.2 The certificate is valid for 5 years from date of issue or renewal unless previously cancelled or suspended Custom milling permits.
Registration/Renewal as a Custom Milling Center (SI 329,2002; SI 178,2006)
1.1 Every Custom Milling Plant must be registered before it can operate.
1.2 The Custom Milling licenses expire every 31stDecember.
1.3 Renewal of Custom Milling Licenses are done every 12 months to the Mining Commissioner for the district under which they are registered.
1.4 Registration and/ or renewal requirements are as follows:
The Custom Mill shall pay a renewal fee that the Ministry shall decide from time to time.
The Custom Mill shall obtain an Environmental Impact Assessment Certificate (EIA).
The Mill shall be inspected by the Regional Mining Engineer, Regional Surveyor and Regional Metallurgist approved by the Director for Metallurgy.
1.5 Once the Mill complies with these and other requirements, the Secretary shall issue a Registration or Renewal License whichever the case may be.
Gold Jewellery Permit Requirements
Procedure
License To Deal In Precious Stones In Particular To Cut And Polish Rough Diamonds
Requirements
· Vetting by Police,
· Inspection of business premises by C.I.D for suitability & diamond security,
· Submission of Certificate of Incorporation and CR 14, Directorship & Shareholding structure,
NB. Application for this is made to the Permanent Secretary and the license is valid for 10 years.
Summary Of Procedures Of Acquiring A Mining Title
License | AREA | Minerals | APPLICANT REQUIREMENT | Approving authority | Processing | LENGTH OF TENURE | ||
Ordinary / | • 10ha precious
| All |
|
|
| 2 years | ||
Special | metal/stone • 25ha base metal
|
| Legal | Instant (over the |
| |||
prospecting |
| Services | counter) |
| ||||
licence |
|
|
|
| ||||
(IV)
|
|
|
|
| ||||
|
|
|
|
|
| |||
Exclusive | • 65 000ha | All except Coal |
| President | 3 months | Initial period of 3 | ||
Prospecting | • Any defined |
|
|
| years | |||
Order | area (including |
|
|
|
|
| Renewable for a | |
(VI) | Reserved) |
|
|
|
|
| maximum period of | |
|
|
|
|
|
|
| of 3 years | |
Mining | Amalgamation | All | Mining | 3 months | Perpetual | |||
Lease | of contiguous |
|
| Affairs Board |
| Annual renewal | ||
(VIII) | mining |
|
|
|
|
|
| |
| location |
|
|
|
|
|
| |
Special | As Mining | All | Mining | 3 months | Perpetual | |||
Mining | Lease |
| Affairs Board |
| Annual renewal | |||
Lease IX |
|
|
|
|
| |||
Special | Any defined | All | Secretary for | 2 months | Perpetual | |||
Grant | area |
| Mines and MD |
| Annual renewal | |||
(XIX) |
|
|
|
|
| |||
Special | 20 000ha for coal,
| Coal, |
|
| Perpetual | |||
Grant under |
| Mineral | President | 3 months | Annual renewal | |||
Part XX of Act | 100 000ha for CBM | Oils, |
|
|
| |||
(XX) | and Natural Gas | Natural gas |
|
|
| |||
|
|
|
|
|
| |||
|
|
|
|
|
| |||
|
|
|
|
|
|
Details Required In Applying For A Mining Title
TITLE | APPLICATION DET AILS REQUIRED | Approving | PROCESSING |
(Part of Act) |
| Authority | PERIOD |
Ordinary / | Legal | Instant (over the | |
Special | Services | counter) | |
prospecting |
|
| |
licence |
|
| |
|
|
| |
(IV) | For companies – Certificate of registration |
|
|
Exclusive Prospecting Order (VI) | President | 3 months | |
|
| ||
|
| ||
|
| ||
|
| ||
|
|
| |
Mining Lease | Mining | 3 months | |
(VIII) | Affairs Board |
| |
|
|
| |
|
|
| |
|
|
| |
Special Mining | Mining | 3 months | |
Lease | Affairs Board |
| |
(IX) |
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
Special Grant | Secretary for | 2 months | |
(XIX) | Mines and MD |
| |
Special Grant | President | 3 months | |
|
|
| |
under Part XX |
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|